Information on NPP Dukovany 21/2/2012

21. 2. 2012

Units 1, 2, 4 are operated at full rated power. The Unit 3 is in a startup mode after refuelling. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 338 686 076 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

 

  • Unit 1 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 503 MWe
  • Unit 2 is in Mode 1 – power operation, Reactor power is 94,2 %, Turbine generator output – 436 MWe
  • Unit 3 is in Mode 1 – The Unit is in a startup mode after refuelling., Reactor power is 3,7 %, Turbine generator output – 0 MWe
  • Unit 4 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 506 MWe

 

Electricity production since the beginning of the year:  2 034 897 MWh.

 

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany