Units 1, 2, 4 are operated at full rated power. Unit 3 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El. production since the beginning of operation: 310 932 614 MWh.
Information on parameters of Unit 1-4, today at 7:00 hrs:
- Unit 1 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 468 MWe
- Unit 2 is in Mode 1 - power conditions, Reaktor power is 100 %, Turbine generator output – 462 MWe
- Unit 3 is in Mode 6 - refueling – shutdown with primary circuit open
- Unit 4 is in Mode 1 - power conditions, Reactor power is 100 %, Turbine generator output – 456 MWe
Electricity production since the beginning of the year: 2 825 648 MWh.
Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany