Information on NPP Temelín 169 / 2010
Homepage » CEZ Group » Media » Nuclear Power Plant news » Information on NPP Temelín 169 / 2010
31. 8. 2010
Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of the reactor fuel. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1 today on August 31, 2010 at 15:30 o‘clock:
- Unit is in Mode 6
- Reactor power is 0 %
- Turbine generator output - 0 MWe
- Electricity production since the beginning of the year: 4 726 143 MWh
Information on parameters at Unit 2 today on August 31, 2010 at 15:30 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output - 1009 MWe
- Electricity production since the beginning of the year: 4 223 567 MWh
Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín