Current News

10
April 2014

Today ČEZ decided to cancel procurement procedure for construction of Temelin nuclear power plant

Today ČEZ cancelled the procurement procedure in accordance with Public Procurement Act for construction of two nuclear units in the location of Temelin nuclear power plant and subsequently sent a relevant notice on cancellation of procurement procedure for public contract to participants. Information was received by all participants – consortium of Westinghouse Electric Company LLC and Westinghouse Electric Czech Republic s.r.o., consortium of ŠKODA JS, Atomstroyexport and Gidropress and also earlier excluded AREVA NP.

2
July 2013

ČEZ continues its negotiations with bidders in its tender for the completion of Units 3 and 4 of the Temelín NPP

ČEZ continues its intensive negotiations with bidders under its tender for the completion of Units 3 & 4, which started in early April 2013; nevertheless, there are still numerous open issues.

30
May 2013

Both nuclear power plants in the Czech Republic are continuously upgraded

The two nuclear power plants in the Czech Republic repeatedly rank among the most reliable nuclear operations in the world. However, maintaining their safety and performance requires ongoing capital expenditures. This applies to all power plants anywhere in the world. Since the Dukovany and the Temelín nuclear power plants have been launched, ČEZ has invested nearly CZK 30 billion in upgrading these facilities. The capital invested has made hundreds of major and minor improvements possible.

25
March 2013

Today, ČEZ has sent its preliminary bid evaluation reports for Temelín Units 3&4

ČEZ has today informed the bidders that still continue in the tender about its assessment and preliminary evaluation of their bids for the completion of two nuclear units at the Temelín Nuclear Power Plant.

18
December 2012

ČEZ plans to complete its preliminary evaluation of the bids for Temelín Units 3&4 by the end of February

ČEZ is going to finalize its preliminary evaluation of the bids to complete two nuclear units at the Temelín Nuclear Power Plant in late February next year. The original internal plan foresaw the evaluation to be completed in late 2012 or early 2013. However, this milestone did not include a period of time for excluding one bidder in the early phase and the subsequent means of remedy, which actually happened.

30
November 2012

ČEZ has applied for a permit to place two new units in Temelín

ČEZ has today lodged an application with the State Office for Nuclear Safety for a permission to place two new nuclear units on the premises of the Temelín NPP. This marks an end to five years of preparation work, and the company is now ready for the licensing process according to the Atomic Act.

5
October 2012

Areva Failed to Comply with Public Contract Requirements Defined for Building Temelín NPP Units 3 and 4; ČEZ Had to Disqualify This Bidder

ČEZ has today informed Areva that they have in their bid failed to meet statutory requirements for building two new units of the Temelín Nuclear Power Plant. Moreover, Areva has not fulfilled some other crucial criteria defined in the tender. Since the award procedure has been conducted in accordance with the Public Procurement Act, Areva’s bid had to be excluded from further evaluation.

3
July 2012

ČEZ Has Today Opened Bids From Three Qualified Bidders Interested in Completing the Temelín NPP and have Thus Started the Bid Evaluation Process

On July 3, ČEZ opened bids for the public contract for completing the Temelín Nuclear Power Plant in the presence of the bidders’ - Areva, a consortium of the Westinghouse Electric Company, LLC and WESTINGHOUSE ELECTRIC ČR, and a consortium of ŠKODA JS, Atomstroyexport, and Gidropress. From this moment on, a team of experts will thoroughly examine, evaluate, and discuss the bids with the bidders in order to achieve their optimization.

2
July 2012

ČEZ Has Received Bids for the Public Contract for Completing the Temelín Nuclear Power Plant

Today, on Monday, July 2, was the deadline for submitting bids for completing the Temelín Nuclear Power Plant. Three qualified bidders have submitted their bids by today’s deadline for the biggest contract in the history of ČEZ and the entire Czech Republic – Areva, a consortium of the Westinghouse Electric Company, LLC and WESTINGHOUSE ELECTRIC ČR, and a consortium of ŠKODA JS, Atomstroyexport, and Gidropress. Tomorrow, the envelopes with their bids will be opened in their presence.

31
October 2011

CEZ Invites Qualified Candidates to Submit Bids to Complete the Temelín Nuclear Power Plant

CEZ has today handed over an Invitation to Submit Bid with the relevant Tender Documentation to the three candidates that have qualified for the tender for the public contract of “Completion of the Temelín Nuclear Power Plant”.

Předchozí