15. 12. 2005

Information on NPP Temelín 242 / 2005

Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.

December 14, 2005

Information on parameters at Unit 1 today on December 14, 2005 at 13:15 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 980 MW
· Electricity production since the beginning of the year: 5 668 126 MWh

Information on parameters at Unit 2 today on December 14, 2005 at 13:15 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 86 %
· Turbine generator output - 819 MW · Electricity production since the beginning of the year: 4 892 170 MWh

Milan Nebesář
ČEZ, a. s. Spokesman