Information on NPP Dukovany 8/1/2018
8. 1. 2018
Units 1, 2, 3, 4 are operated on power operation. All systems are working in accordance with operational needs of the units. Electricity production since the beginning of the operation: 419 340 072 MWh.
Information on parameters of Unit 1-4, today at 7:00 hrs:
- Unit 1 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 501 MWe
- Unit 2 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 505 MWe
- Unit 3 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 497 MWe
- Unit 4 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 502 MWe
Electricity production since the beginning of the year: 267 566 MWh.
Ing. Jiří Bezděk
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany