Information on NPP Dukovany 10/07/2018

10. 7. 2018

Units 1, 2, 3 are operated on power operation. Unit 4 is in outage. All systems are working in accordance with operational needs of the units. Electricity production since the beginning of the operation: 426 440 671 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

  • Unit 1 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 487 MWe
  • Unit 2 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 487 MWe
  • Unit 3 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 488 MWe
  • Unit 4 is in Mode 6 – outage

Electricity production since the beginning of the year:  7 368 165 MWh.

Ing. Jiří Bezděk
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany