2. 9. 2010

Information from the NPP Temelín 171 / 2010

Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of the reactor fuel. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on September 2, 2010 at 13:45 o‘clock:

  • Unit is in Mode 6
  • Reactor power is 0 %
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 4 726 143 MWh

Information on parameters at Unit 2 today on September 2, 2010 at 13:45 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1006 MWe
  • Electricity production since the beginning of the year: 4 272 068 MWh


Marek SVITÁK
ČEZ Group Spokesman
Nuclear Power Plant Temelín