4. 12. 2009

Information from the NPP Temelín 233 / 2009

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on December 4, 2009 at 09:30 o‘clock:

  • Unit is in Mode 1- power operation
  • Reactor power is 100 %
  • Turbine generator output - 1015 MWe
  • Electricity production since the beginning of the year:  5 940 852 MWh

Information on parameters at Unit 2 today on December 4, 2009 at 09:30 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1016 MWe
  • Electricity production since the beginning of the year:  6 055 143 MWh

 