22. 12. 2011

Information on NPP Dukovany 22/12/2011

Units 1, 2, 3, 4 are operated at full rated power. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 336 187 857 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

 

  • Unit 1 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 504 MWe
  • Unit 2 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 457 MWe
  • Unit 3 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 497 MWe
  • Unit 4 is in Mode 1 – power operation, Reactor power is 100 %, Turbine generator output – 504 MWe

 

 

Electricity production since the beginning of the year:  13 905 334 MWh.

 

 

Ing. Petr Spilka
Spokesman of the ČEZ Group
Nuclear Power Plant Dukovany