Information on NPP Dukovany 30/11/2010

Units 1, 2 are operated at full rated power. The Unit 3 is in a startup mode after refuelling. The Unit 4 is in planned outage. All auxiliary systems are working in accordance with operational needs of units. El.production since the beginning of operation: 321 190 302 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

 

  • Unit 1 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 468 MWe
  • Unit 2 is in Mode 1 - power operation, Reaktor power is 100 %, Turbine generator output – 448 MWe
  • Unit 3 is in Mode 3 - cold shutdown
  • Unit 4 is in Mode 7 – total fuel removal from reactor core

 

 

Electricity production since the beginning of the year:  13 083 336 MWh.

 