15. 7. 2009

Information on NPP Temelín 136 / 2009

Unit 2 was re-connected to the power grid this morning at 04:21 o’clock. The outage has been completed after 81.31 days, i.e. by 16.5 hours earlier than planned in the schedule.

In the course of today, the operations personnel will increase the unit output to 80 per cent RTP. The power tests will follow at this power level. They will end by Saturday, July 18, and, subsequently, the unit output will be increased to 100 per cent RTP.

“It was a hard outage including a number of activities that were unique and that won’t be repeated in the next years. Those were especially the reconstruction of low pressure turbines rotors and modernization of the refueling machine. Also, implementation of a range of additional technical measures to enhance the equipment reliability that result from the proceeding of the project SAFELY 15TERA has been included. We succeeded in completing of all planned activities as well as in meeting the planned outage time. Even from this point of view, it was a successful outage,” Director of Temelín NPP Miloš Štěpanovský assessed briefly the completed outage of Unit 2.

Unit 1 is in operation at planned power level. All auxiliary systems of the power plant are working in accordance with the operation needs.


Information on parameters at Unit 1 today on July 15, 2009 at 10:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1003 MWe
  • Electricity production since the beginning of the year:  4 665 297 MWh

Information on parameters at Unit 2 today on July 15, 2009 at 10:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 62 %
  • Turbine generator output - 562 MWe
  • Electricity production since the beginning of the year:  2 637 372 MWh

 

 

Václav BROM
ČEZ Group Spokesman
Nuclear Power Plant Temelín