Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on January 22, 2009 at 11:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1017 MWe
  • Electricity production since the beginning of the year: 504 289 MWh

Information on parameters at Unit 2 today on January 22, 2009 at 11:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1008 MWe
  • Electricity production since the beginning of the year: 507 234 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín