Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of a part of the reactor fuel. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on August 4, 2009 at 14:15 o‘clock:

  •      Unit is in Mode 6
  •      Reactor power is 0 %
  •      Turbine generator output - 0 MWe
  •      Electricity production since the beginning of the year: 5 072 238 MWh

Information on parameters at Unit 2 today on August 4, 2009 at 14:15 o‘clock:

  •      Unit is in Mode 1 - power operation
  •      Reactor power is 100 %
  •      Turbine generator output - 1005 MWe

Electricity production since the beginning of the year: 3 098 181 MWh