Information on NPP Temelín 169 / 2013

Unit 2 is in operation at planned power level. At Unit 1, a planned outage is under way, that is connected with the annual refueling of the reactor fuel. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on August 29, 2013 at 8:30 o‘clock:

  • Unit is at the planned power level
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 4 660 484 MWh

Information on parameters at Unit 2 today on August 29, 2013 at 8:30 o‘clock:

  • Unit is at the planned power level
  • Turbine generator output - 1057 MWe
  • Electricity production since the beginning of the year: 4 539 472 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín