This morning, the last balancing run has been completed on the turbine set. At 9 o’clock, primary testing of the turbine generator started. In compliance with the schedule, the testing will be completed tomorrow and the unit will be synchronized to the power distribution grid.
Information on parameters at Unit 1 today on October 19, 2009 at 9:45 o‘clock:
- Unit is in Mode 1
- Reactor power is 30 %
- Turbine generator output - 0 MWe
- Electricity production since the beginning of the year: 5 072 238 MWh
Information on parameters at Unit 2 today on October 19, 2009 at 9:45 o‘clock:
- Unit is in Mode 1 - power operation
- Reactor power is 100 %
- Turbine generator output – 1010 MWe
- Electricity production since the beginning of the year: 4 936 280 MWh
Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín