9. 11. 2010

Information on NPP Temelín 215 / 2010

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on November 9, 2010 at 12:30 o‘clock:

  • Unit is in Mode 1- power operation
  • Reactor power is 100 %
  • Turbine generator output - 1016 MWe
  • Electricity production since the beginning of the year: 5 336 445 MWh

Information on parameters at Unit 2 today on November 9, 2010 at 12:30 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1013 MWe
  • Electricity production since the beginning of the year: 5 925 213 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín