2. 12. 2005

Information on NPP Temelín 234/2005

Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.

December 2, 2005

Unit 1 and Unit 2 are in operation at planned power level. All auxiliary systems are working in accordance with the operation modes of individual units.

Information on parameters at Unit 1 today on December 2, 2005 at 07:30 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 979 MW
· Electricity production since the beginning of the year: 5 385 680 MWh

Information on parameters at Unit 2 today on December 2, 2005 at 07:30 o’clock:
· Unit is in Mode 1 - power operation
· Reactor power is 87 %
· Turbine generator output – 843 MW
· Electricity production since the beginning of the year: 4 654 927 MWh

Milan Nebesář
ČEZ, a.s. Spokesman