22. 12. 2010

INFORMATION ON NPP TEMELÍN 245 / 2010

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on December 22, 2010 at 14:00 o‘clock:

  • Unit is in Mode 1- power operation
  • Reactor power is 100 %
  • Turbine generator output - 1014 MWe
  • Electricity production since the beginning of the year: 6 384 091 MWh

Information on parameters at Unit 2 today on December 22, 2010 at 14:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1015 MWe
  • Electricity production since the beginning of the year: 6 974 266 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín