15. 2. 2010

INFORMATION ON NPP TEMELÍN 31 / 2010

Both Unit 1 and 2 are in operation at full rated power. The auxiliary systems are working in accordance with the operation needs of individual units.

At the weekend, all planned works have been carried out during the Unit 1 outage. Unit 1 restored the electricity delivery on Sunday at 5:54 o’clock and, since 12:15 o’clock, it operates at full power.

Information on parameters at Unit 1 today on February 15, 2010 at 9:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1014 MWe
  • Electricity production since the beginning of the year: 1 063 657 MWh

Information on parameters at Unit 2 today on February 15, 2010 at 9:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1016 MWe
  • Electricity production since the beginning of the year: 1 089 694 MWh

  

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín