24. 3. 2009

Information on NPP Temelín 57 / 2009

Unit 1 is in operation at full rated power. Unit 2 is operated in the mode of power effect of reactivity. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on March 24, 2009 at 10:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1020 MWe
  • Electricity production since the beginning of the year: 1 967 470 MWh

Information on parameters at Unit 2 today on March 24, 2009 at 10:00 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 98 %
  • Turbine generator output - 989 MWe
  • Electricity production since the beginning of the year: 1 986 410 MWh

 

Marek Sviták
Spokesman of the ČEZ Group
Nuclear Power Plant Temelín