22. 3. 2006

Information on NPP Temelín 58/2006

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems are working in accordance with the operation needs of individual units.

March 22, 2006

Both Unit 1 and 2 are in operation at full rated power. All auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on March 22, 2006 at 07:15 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 96 %
· Turbine generator output - 980 MW
· Electricity production since the beginning of the year: 1 784 114 MWh

Information on parameters at Unit 2 today on March 22, 2006 at 07:15 o‘clock:
· Unit is in Mode 1 - power operation
· Reactor power is 97 %
· Turbine generator output - 979 MW
· Electricity production since the beginning of the year: 1 164 442 MWh

Milan Nebesář
Spokesman of the Temelín NPP