CEZ Group expanded to Turkey in 2008 and today it operates here in the field of electricity generation.

Electricity production

Electricity production is provided by Akenerji Elektrik Üretim and its subsidiaries. Through them CEZ Group co-owns power plants with a total installed capacity of 1,242 MW. The portfolio is dominated by the Egemer CCGT plant with an installed capacity of 904 MW and seven hydroelectric plants with an installed capacity of 288.9 MW. Wind power makes up 28.2 MW.

Overview of biggest co-owned energy sources in Turkey

Power plant Type Installed capacity (MW) Operational from
Egemer CCGT 904 2014
Ayyıldız RES wind 5 x 3; 4 x 3.3 2009, 2016
Bulam hydro 7.03 2010
Burc Bendi hydro 27.33 2010
Feke I hydro 2 x 14.5 2012
Feke II hydro 69.35 2010
Gökkaya hydro 2 x 14 2012
Himmetli hydro 2 x 13.5 2012
Uluabat hydro 97.02 2010