15. 9. 2021

INFORMATION ON NPP DUKOVANY 15/09/2021

Units 1, 2, 4 are operated on power operation. The Unit 3 is in outage. Electricity production since the beginning of the operation: 472 460 528 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 485 MWe
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 480 MWe 
Unit 3 is in Mode 5 - outage
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 495 MWe
 

Electricity production since the beginning of the year: 10 279 035 MWh.