9. 7. 2021

Information on NPP Dukovany 9/7/2021

Units 1, 2, 4 are operated on power operation. Unit 3 is in planned outage. Electricity production since the beginning of the operation: 469 461 479 MWh.

Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 482 MWe
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 477,9 MWe 
Unit 3 is in Mode 3 - outage
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 469 MWe
 

Electricity production since the beginning of the year: 7 279 986 MWh.