INFORMATION ON NPP TEMELÍN 135 / 2012

The Unit 2 is in operation at full rated power. The Unit 1 is operated in the mode of power effect of reactivity. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1 today on July 16, 2012 at 9:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1016 MWe
  • Electricity production since the beginning of the year: 4 736 876 MWh

Information on parameters at Unit 2 today on July 16, 2012 at 9:15 o‘clock:

  • Unit is in Mode 1 - power operation
  • Reactor power is 100 %
  • Turbine generator output - 1015 MWe
  • Electricity production since the beginning of the year: 3 619 793 MWh

 

Petr Šuleř
ČEZ Group
Nuclear Power Plant Temelín

You can find the current information on operation of the Temelín NPP on the Internet web site www.cez.cz.