7/16/2020
INFORMATION ON NPP TEMELÍN 137 / 2020
Unit 1 is in operation at full rated power. Unit 2 is in the planned outage for refuelling. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in operation
- Turbine generator output – 1076 MWe
- Electricity production since the beginning of the year: 3 355 378 MWh
Information on parameters at Unit 2:
- Unit is in the planned outage
- Turbine generator output - 0 MWe
- Electricity production since the beginning of the year: 4 272 380 MWh
News on the topic
Temelín is scheduled to refuel the reactor of Unit 2
The Temelín Unit 1 restored electricity production, despite the coronavirus, the technicians kept to the planned deadlines
ČEZ Applies for Permission to Construct Two New Blocks at the Dukovany Nuclear Power Station
GE Hitachi Nuclear Energy and ČEZ Announce Small Modular Reactor Technology Collaboration in the Czech Republic