14/08/2020
INFORMATION ON NPP TEMELÍN 158 / 2020
Both Unit 1 and 2 are in operation at planned power. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in operation
- Turbine generator output – 1065 MWe
- Electricity production since the beginning of the year: 4 102 299 MWh
Information on parameters at Unit 2:
- Unit is in operation
- Turbine generator output - 1078 MWe
- Electricity production since the beginning of the year: 4 369 765 MW
News on the topic