Unit 1 is in operation. Unit 2 is in the planned outage for refueling. The auxiliary systems are working in accordance with the operation needs of the individual units.
Information on parameters at Unit 1:
- Unit is in operation
- Turbine generator output – 1084 MWe
- Electricity production since the beginning of the year: 4 675 021 MWh
Information on parameters at Unit 2:
- Unit is in the outage
- Turbine generator output – 0 MWe
- Electricity production since the beginning of the year: 4 559 780 MWh
News on the topic
The country’s largest parking complex with a photovoltaic power plant built at the Dukovany Nuclear Power Plant
ČEZ Started Security Screening of Potential Bidders for a New Nuclear Unit in Dukovany
Elektrárna Dukovany II applied for a zoning permit for a new nuclear source at the Dukovany site today
Temelín's Unit 1 restored the production of electricity. The outage has taken place in the mode of full testing of both plant and suppliers’ staff