Both Unit 1 and 2 are in operation at planned power. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in operation
- Turbine generator output – 1081 MWe
- Electricity production since the beginning of the year: 5 325 081 MWh
Information on parameters at Unit 2:
- Unit is in operation
- Turbine generator output - 1094 MWe
- Electricity production since the beginning of the year: 5 650 356 MWh