15. 5. 2020

INFORMATION ON NPP TEMELÍN 94 / 2020

The Unit 2 is in the operation. The start-up of Unit 1 was interrupted and the compensation equipment in the non-nuclear part of the power plant will be replaced at the weekend. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in the outage
  • Turbine generator output – 0 MWe
  • Electricity production since the beginning of the year: 1 857 038 MWh

 

  • Information on parameters at Unit 2:
  •  Unit is in the operation
  • Turbine generator output - 1084 MWe
  • Electricity production since the beginning of the year: 3 531 792 MWh