EPR1 - Decommission

18. 5. 2020  CEZ ‘s Prunerov 1 power plant, B3,4,5 6 98,3 MW units shall be decommissioned as of July 1st, 2020. The power plant then enters into liquidation.

Activation time EME B11 and EDE

24. 4. 2020  As part of the operational measures taken the activation (synchronisation) time of unit Melnik 3, B11 and Detmarovice B2,3 and 4 shall be extended to 36, resp. 72 hours. The measure shall last until 14.6., resp. 30.6.2020.


Available capacity
Actual production