10/26/2023
Information on NPP DUKOVANY 26/10/2023
Units 1, 2, 3 are in the operation. Unit 4 is in the planned outage for refuelling. Electricity production since the beginning of the operation: 503 741 763 MWh.
Information on parameters of Unit 1-4, today at 7:00 hrs:
Unit 1 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 494 MWe
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 489 MWe
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 490 MWe
Unit 4 is in Mode 7 - outage
Electricity production since the beginning of the year: 11 963 933 MWh.
News on the topic
Czech Nuclear Power Plants Comply with International Environmental Protection Standards