Both Unit 1 and 2 are in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in the operation
- Turbine generator output – 1079 MWe
- Electricity production since the beginning of the year: 2 655 698 MWh
Information on parameters at Unit 2:
- Unit is in the operation
- Turbine generator output – 1080 MWe
- Electricity production since the beginning of the year: 4 211 303 MWh
News on the topic
Elektrárna Dukovany II applied for a zoning permit for a new nuclear source at the Dukovany site today
Temelín's Unit 1 restored the production of electricity. The outage has taken place in the mode of full testing of both plant and suppliers’ staff
EUROVIA CS Group to be driven by emissions-free power from ČEZ
Temelín is scheduled to refuel the reactor of Unit 1. Anti-Covid measures are tightened up for the outage