INFORMATION ON NPP TEMELÍN 139 / 2020

Unit 1 is in operation at full rated power. Unit 2 is in the planned outage for refuelling. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in operation
  • Turbine generator output – 1066 MWe
  • Electricity production since the beginning of the year: 3 458 823 MWh

Information on parameters at Unit 2:  

  • Unit is in the planned outage
  • Turbine generator output - 0 MWe
  • Electricity production since the beginning of the year: 4 272 380 MWh