Unit 1 is in the planned outage for refuelling. Unit 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.

Information on parameters at Unit 1:

  • Unit is in the planned outage
  • Turbine generator output – 0 MWe
  • Electricity production since the beginning of the year: 1 793 456 MWh

Information on parameters at Unit 2:

  • Unit is in the operation
  • Turbine generator output - 1077 MWe
  • Electricity production since the beginning of the year: 3 427 016 MWh