5/18/2020
INFORMATION ON NPP TEMELÍN 95 / 2020
The Unit 1 and Unit 2 are in the operation. After a three-day interruption of the start-up, Unit1 resumed the electricity production today at 8:28 am. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in the operation
- Turbine generator output – 670 MWe
- Electricity production since the beginning of the year: 1 857 686 MWh
Information on parameters at Unit 2:
- Unit is in the operation
- Turbine generator output - 1084 MWe
- Electricity production since the beginning of the year: 3 609 790 MWh
News on the topic
The Temelín Unit 1 restored electricity production, despite the coronavirus, the technicians kept to the planned deadlines
ČEZ Applies for Permission to Construct Two New Blocks at the Dukovany Nuclear Power Station
GE Hitachi Nuclear Energy and ČEZ Announce Small Modular Reactor Technology Collaboration in the Czech Republic
Temelín´s Unit 2 restored production of electricity