12/19/2024
INFORMATION ON NPP TEMELÍN 245 / 2024
Both Unit 1 and 2 is in the operation. The auxiliary systems are working in accordance with the operation needs of individual units.
Information on parameters at Unit 1:
- Unit is in the operation
- Turbine generator output – 1086 MWe
- Electricity production since the beginning of the year: 7 133 004 MWh
Information on parameters at Unit 2:
- Unit is in the operation
- Turbine generator output - 1095 MWe
- Electricity production since the beginning of the year: 7 191 078 MWh
News on the topic
The Temelín Unit 2 produces electricity again. It will be in operation for fourteen months, two months longer than before.
ČEZ will shut down Unit 2 this evening for inspections and replacement of fuel assemblies
ČEZ evaluated bids for the construction of a new nuclear unit and named its preferred bidder, with results submitted to Ministry of Industry and Trade
The first Temelín Unit produces electricity again. It has been shut down for two months to inspect and replace fuel assemblies